26. Critical path
A. is always longest
B. is always shortest
C. may be longest
D. may be shortest
Explanation:
27. Slack time refers to
A. an activity
B. an event
C. both event and activity
D. none of the above
Explanation:
28. Which of the following excavators is most suitable for digging under water?
A. Drag line
B. Hoe
C. Clam shell
D. Dipper shovel
Explanation:
29. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
A. total float
B. free float
C. interfering float
D. independent float
Explanation:
30. The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack Of these statements
A. (i), (ii) and (iv) are correct
B. (ii), (iii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i), (ii) and (iii) are correct
Explanation: