Construction Planning and Management - Interview Questions and Answers
Prepare for your technical interview with these Construction Planning and Management questions.
Ready to test your skills?
Take a timed mock test specifically for Construction Planning and Management.
46. Crash project duration is obtained by summing the
Explanation:
47. If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is
Explanation:
48. If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
Explanation:
49. The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
Explanation:
50. A machine is purchased for Rs. 10,000,00/- and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000/-. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
Explanation: