66. Consider the following statements :
In the critical path method of construction planning, Free Float can be.
# greater than Total Float.
# greater than Independent Float
# equal to Total Float.
# less than Independent Float. Of these statements
Explanation:
67. In the network shown in Fig., the concurrent and preceding activities corresponding to activity 2-4 are respectively
Explanation:
68. If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
Explanation:
69. Consider the following statements:
In the bar chart planning
# interdependence of the operations cannot be portrayed.
# progress of work can be measured.
# spare time of the activities can be determined.
# schedule cannot be updated.
Of these statements
Explanation:
70. At a work site, statistical quality control of concrete means
Explanation: