16. In the network shown in Fig. the earliest start time of activity 5-6 is (the number on the arrow shows duration of the activity)
A. 7
B. 8
C. 9
D. 5
Explanation:
17. With reference to the network shown in Fig. , which statement is incorrect ?
A. Events 3 and 4 occur after event 2.
B. Event 7 can occur after event 4.
C. Event 7 precedes event 6.
D. Event 5 follows event 3.
Explanation:
18. The time with which direct cost does not reduce with the increase in time is known as
A. crash time
B. normal time
C. optimistic time
D. standard time
Explanation:
19. What estimate would you give for the variance in above problem ?
A. 81
B. 54
C. 36
D. 9
Explanation:
20. The process of incorporating changes and rescheduling or replanning is called
A. resource levelling
B. resource smoothening
C. updating
D. critical path scheduling
Explanation: