61. A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels : 25000 kg Scraper wheels : 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is
A. 10000 kg
B. 12500 kg
C. 22500 kg
D. 5000 kg
Explanation:
62. A four wheel trac*or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
A. 20 kg/tonne
B. 30 kg/tonne
C. 40 kg/tonne
D. 50 kg/tonne
Explanation:
63. An excavator costs Rs. 20,00,000/- and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is
A. Rs. 8,43,750/-
B. Rs. 8,75,000/-
C. Rs. 10,50,000/-
D. Rs. 11,56,250/-
Explanation:
64. A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
A. Rs.1740
B. Rs.3480
C. Rs.5220
D. Rs.6960
Explanation:
65. During the construction period, price variation clause in contracts caters to
A. increase in rates of only important materials
B. variation in cost in materials element, labour element and petrol-oil-lubricant element
C. variation in total cost of the project on an ad hoc basis
D. rate of inflation
Explanation: