Construction Planning and Management - Interview Questions and Answers
Prepare for your technical interview with these Construction Planning and Management questions.
Ready to test your skills?
Take a timed mock test specifically for Construction Planning and Management.
61. A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is:
Drive wheels : 25000 kg
Scraper wheels : 10000 kg
If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is
Explanation:
62. A four wheel trac*or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
Explanation:
63. An excavator costs Rs. 20,00,000/- and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is
Explanation:
64. A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
Explanation:
65. During the construction period, price variation clause in contracts caters to
Explanation: