Construction Planning and Management - Interview Questions and Answers

Prepare for your technical interview with these Construction Planning and Management questions.

Ready to test your skills?

Take a timed mock test specifically for Construction Planning and Management.

Start Mock Test
76. In resources levelling
A. total duration of project is reduced
B. total duration of project is increased
C. uniform demand of resources is achieved
D. cost of project is controlled
Explanation:
77. Which one of the following is not an excavating and moving type of equipment ?
A. Bulldozer
B. Clam shell
C. Scraper
D. Dump truck
Explanation:
78. If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
A. 3.5 and 5/6
B. 5 and 25/36
C. 3.5 and 25/36
D. 4 and 5/6
Explanation:
79. Consider the following operations : # Drilling # Blasting # Mucking # Placing steel # Placing concrete The correct sequence of these operations in tunnel construction is
A. 1,2,4,3,5
B. 1,3,2,4,5
C. 1,2,3,4,5
D. 1,3,4,2,5
Explanation:
80. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
A. 8 days
B. 9 days
C. 10 days
D. 15 days
Explanation: