86. Sensitivity analysis is a study of
A. comparison of profit and loss
B. comparison of assets and liabilities
C. change in output due to change in input
D. economics of cost and benefits of the project
Explanation:
87. The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted, and pneumatic tyre-mounted machines would be respectively
A. 80 and 90
B. 90 and 80
C. 85 and 75
D. 75 and 83
Explanation:
88. Grader is used mainly for
A. trimming and finishing
B. shaping and trimming
C. finishing and shaping
D. finishing, shaping and trimming
Explanation:
89. In the network shown in Fig. independent float for the activity 3-5 will be (the number on the arrow shows the duration of activity)
A. 0
B. 1
C. 2
D. none of the above
Explanation:
90. Consider the following features/factors : # Projects are of the non-repetitive type. # Time required need not be known. # Time required is known precisely. # Events have been established for planning. # Emphasis is given to activities of project. PERT is preferred for planning because of
A. 1,2 and 4
B. 3,4 and 5
C. 1,3 and 4
D. 1,2 and 5
Explanation: