81. The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be
Explanation:
82. The basic action involved in sheep foot rolling is
Explanation:
83. In the time-cost optimization, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
Explanation:
84. The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is
Explanation:
85. Consider the following statements:
Wheeled tractors are replacing crawler tractors because
# wheeled tractors travel faster.
# crawler tractors are more expensive.
# track parts of a crawler wear out quickly.
# crawler tractors have stick control.
Of these statements
Explanation: