81. The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be
A. Rs. 8,800/-
B. Rs. 7,600/-
C. Rs. 6,400/-
D. Rs. 5,000/-
Explanation:
82. The basic action involved in sheep foot rolling is
A. Kneading
B. Pressing
C. Tamping
D. Vibration
Explanation:
83. In the time-cost optimization, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
A. longest duration
B. highest cost slope
C. least cost slope
D. shortest duration
Explanation:
84. The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is
A. 3425 kg
B. 5515 kg
C. 4350 kg
D. 2975 kg
Explanation:
85. Consider the following statements: Wheeled tractors are replacing crawler tractors because # wheeled tractors travel faster. # crawler tractors are more expensive. # track parts of a crawler wear out quickly. # crawler tractors have stick control. Of these statements
A. 1,3 and 4 are correct
B. 2, 3 and 4 are correct
C. 1,2 and 3 are correct
D. 1, 2 and 4 are correct
Explanation: