21.Activity s,lack or float of any event on a PERT/CPM chart is represented by

latest start time of succeeding event -earliest finish time of preceding event activity time
latest start time of the event - earliest start time of the event
latest finish time of event - earliest finish time of the event
anyone of the above
none of the above.

22.Criticalpath on PERT/CPM chart is obtained by joining the events having

maximum slack
minimum slack
average slack
no slack
judgement and experience.

23.Critical Path Net Work helps an engineer

to concentrate his attention on critical activities
to divert the resources from non-critical advanced activities to critical activities
to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
all of the above
none of the above.

24.Critical path moves along the activities having total float of

positive value
negative value
zero value
same value
none of the above.

More Production Technology QUESTIONS AND ANSWERS available in next pages