6.A CPM family includes

CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
MCE (Minimum Cost Expenditure)
CPS (Critical Path Scheduling)
all of the above.

7.The time which results in the least possible direct cost of an activity is known as

normal time
slow time
crash time
standard time
none of the above.

8.Pessimistic time is

the maximum time which an activity might require
the average time required for a job
the most probable time considering all conditions
the minimum time in which an ac�tivity can possibly be accomplished
the earliest finish.

9.Positive slack on a PERT indicates that project is

ahead of schedule
beyond schedule
as per schedule
on critical path
none of the above.

10.Slack of various events on the critical path in PERT/CPM chart

increases continuously
decreases continuously
remains constant
may increase or decrease depending on various factors
unpredictable.

More Production Technology QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Too many of us are not living our dreams because we are living our fears.- Les Brown