Mechanical Engineering Questions And Answers :: Production Technology: part5



Mechanical Engineering : Production Technology QUESTIONS AND ANSWERS :: part5 : 1 to 5

Following Mechanical Engineering Multiple choice objective type questions and answers will help you in BSNL JTO, GATE 2024 and IES 2024 examinations :

1.Slack represents the difference between the

latest allowable time and the normal expected time
latest allowable time and the earliest expected time
proposed allowable time and the earliest expected time
normal allowable time and the latest expected time
project initiation tune and actual starting time.

2.A big advantage of PERT over Gantt charts is that in the former case

activities and events are clearly shown
early start and late finish of an activity are clearly marked
activity times are clear
critical path can be easily determined
inter-relationship among activities is clearly shown.

3.In queuing theory, the nature of the waiting situation can be studied and analyzed mathematically if

complete details'of items in, waiting line are known
arrival and waiting times are known and can be grouped to form a waiting line model
all variables and constants are known and form a linear equation
the laws governing arrivals, service times, and the order in which the arriving units are taken into source are known
all of the above.

4.The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as

Dry work Plan
Halsey Premium Plan
Taylor Plan
Bedaux Plan
Rowan Plan.

5.The simplex method is the basic method for

value analysis
operation research
linear programming
model analysis
none of the above.

More Production Technology QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
The only place where success comes before work is in the dictionary.- Vidal Sassoon