11.Discrepancies of bar chart techniques are

consequential effects of lack in one activity on omer
consequential effects of lack in one activity on the finish date
free time available for an activity can't be predicted
effective monitoring/controlling can't be done
all of the above.

12.The technique for establishing and maintaining priorities among the various jobs of any project is known as

event flow scheduling technique
critical ratio scheduling
slotting technique for scheduling
short interval scheduling
none of the above.

13.PERT is

an analytic tool in concept
limit up of event oriented diagrams
used for research and development projects
based on three time estimates for activities linking up two events
all of the above.

14.PERT/CPM, techniques can be used for following applications

once through project
maintenance jobs
research and development
all non-technical jobs
all of the above.

15.The assumption in PERT is

a project will always be behind schedule, if left uncorrected
cost of project will always be more than the estimated cost, if no timely corrections are taken
a project can be subdivided into a set of predictable, independent activities
activities are fixed and can't be changed ,
commissioning time can be changed, if activities are behind schedule.

More Production Technology QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Failure defeats losers, failure inspires winners.-Robert T. Kiyosaki