16.An event is indicated on the network by

a straight line
a number enclosed in a circle or a square
a straight line with circles at the ends
a dotted line
an arrow.

17.Pick up the incorrect statement from the following. A critical ratio scheduling

establishes the relative priorities among various activities on a common basis
determines the status of each activity
adjusts automatically changes in activity progress
is a dynamic system
none of the above.

18.O on a PERT/CPM chart represents

an ordinary event
a significant event representing some mile-stone
an event to be transferred to other network chart
dangling event
dummy event.

19.Pick up the correct statement about relationship between various floats

free float = total float
independent float = total float
independent float > free float
free float > total float
independent float < free float.

20.In PERT analysis, critical path is obtained by joining events having

+ve slack
-ve slack
zero slack
dummy activities
critical activities.

More Production Technology QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
If you are not willing to risk the usual you will have to settle for the ordinary- Jim Rohn