26.Crash project duration is obtained by summing the |
| normal durations for all the activities |
| crash durations for all activities |
| crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities |
| crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities. |
More Construction Planning And Management QUESTIONS AND ANSWERS available in next pages
-
Health is the greatest gift, contentment is the greatest wealth -Buddha
- TNTET 2021 - Practice
- SSC CGL 2021 - Practice
- TNPSC Group 2A 2021 - Practice
- IIT JEE
- IIT JEE Q&A
- TNPSC Answer Keys
- TNPSC Group 2 Syllabus
-
TNPSC Q&A

- Online Tests - TNPSC
- Online Tests - GK
- IBPS 2020-2021
- Online Tests - Bank
- Online Tests - RRB NTPC
- Online Tests - UGC NET
- Online Tests - TANCET
- Online Aptitude Test
-
Engineering

-
Programming

-
Basic Science

-
Quiz

- Plus Two Question Papers
- SSLC Question Bank
-
Aptitude Tests

-
Logical Reasoning

-
General Knowledge-Hindi

-
Indian History MCQ

-
Indian Geography MCQ

-
Indian Civics MCQ

-
Indian Economics MCQ

-
CTET Biology MCQ

-
CTET Chemistry MCQ

-
CTET Physics Solved MCQ

-
Arithmetic Tests

- Press Release
- FAQ
- Coaching Centres
- TNPSC Group 1 Syllabus
-
TNPSC Group IV Syllabus

- TRB 2017 in English PDF

- TRB 2017 in Tamil PDF

- TET
- TNTET
Innovation distinguishes between a leader and a follower.-Steve Jobs