1.The time with which direct cost does not reduce with the increase in time is known as

crash time
normal time
optimistic time
standard time

2.What estimate would you give for the variance in above problem ?

81
54
36
9

3.The process of incorporating changes and rescheduling or replanning is called

resource levelling
resource smoothening
updating
critical path scheduling

4.The direct cost of a project with respect to normal time is

minimum
maximum
zero
infinite

5.Which of the following earth moving machines has the shortest cycle time?

Drag line
Hoe
Clam shell
Dipper shovel

More Construction Planning And Management QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Identify your problems but give your power and energy to solutions- Tony Robbins