1.In the network shown in Fig. , the activity 6-8 can be started only when

activity 4�6 is completed
activity 3 - 5 is completed
activity 2�3 is completed
both activities 2�3 and 4�6 are completed

2.In the network shown in Fig. the latest start time of an activity 4-5 is

2
4
8
7

3.In the network shown in Fig. , activity 4-5 can be started only when

activity 3-4 is completed
activity 2�4 is completed
activity 2-3 is completed
activity 2-4 and 2>-A both are com-pleted

4.The area under the Beta - distribution curve is divided into two equal parts by

most likely time
optimistic time
pessimistic time
expected time

5.Latest start of an activity is always

greater than or equal to latest event time of preceding node
less than or equal to latest event time of preceding node
equal to latest event time of preceding node
less than latest event time of preceding node

More Construction Planning And Management QUESTIONS AND ANSWERS available in next pages