Civil Engineering Questions And Answers :: Construction Planning And Management: part4



Civil Engineering : Construction Planning And Management QUESTIONS AND ANSWERS :: part4 : 1 to 5

Following Civil Engineering Multiple choice objective type questions and answers will help you in BSNL JTO, GATE 2024 and IES 2024 examinations :

1.Consider the following activities in a building construction: # Concreting of roof slabs # Brick-jelly lime concrete terracing # Erection of formwork for slab # Construction of parapet wall in terrace The correct sequence of these activities is

1,3,2,4
3,1,4,2
3,1,2,4
1,3,4, 2

2.The most suitable type of equipment for compaction of cohesive soils is

Smooth-wheeled rollers
Vibratory rollers
Sheep foot rollers
Tampers

3.Preliminary project report for a road project must contain

the detailed estimated cost based on detailed design
the several alternatives of the project that have been considered
the soil survey, traffic survey, concept design and approximate cost
the contract documents for inviting tenders

4.In resources levelling

total duration of project is reduced
total duration of project is increased
uniform demand of resources is achieved
cost of project is controlled

5.Which one of the following is not an excavating and moving type of equipment ?

Bulldozer
Clam shell
Scraper
Dump truck

More Construction Planning And Management QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
If you are not willing to risk the usual you will have to settle for the ordinary- Jim Rohn