Civil Engineering Questions And Answers :: Construction Planning And Management: part4



Civil Engineering : Construction Planning And Management QUESTIONS AND ANSWERS :: part4 : 6 to 10

Following Civil Engineering Multiple choice objective type questions and answers will help you in BSNL JTO, GATE 2024 and IES 2024 examinations :

6.Consider the following operations : # Drilling # Blasting # Mucking # Placing steel # Placing concrete The correct sequence of these operations in tunnel construction is

1,2,4,3,5
1,3,2,4,5
1,2,3,4,5
1,3,4,2,5

7.For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

8 days
9 days
10 days
15 days

8.The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

Rs. 8,800/-
Rs. 7,600/-
Rs. 6,400/-
Rs. 5,000/-

9.The basic action involved in sheep foot rolling is

Kneading
Pressing
Tamping
Vibration

10.In the time-cost optimization, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

longest duration
highest cost slope
least cost slope
shortest duration

More Construction Planning And Management QUESTIONS AND ANSWERS available in next pages