16.Which of the following does not represent an activity?

site located
foundation is being dug
the office area is being cleaned
the invitations are being sent

17.Which of the following is a weakness of bar chart ?

interdependencies of activities
project progress
uncertainties
all of the above

18.Which of the following is not a PERT event ?

site investigation started
sessional work completed
bus starts from Jaipur
class is being attended

19.Free float is mainly used to

identify the activities which can be delayed without affecting the total float of preceding activity
identify the activities, which can be delayed without affecting the total float of succeeding activity
establish priorities
identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

20.Earliest finish of an activity is always

greater than earliest event time of the following node
less than earliest event time of the following node
less than or equal to earliest event time of the following node
greater than or equal to earliest event time of the following node

More Construction Planning And Management QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
If your ship doesn’t come in, swim out to meet it!-Jonathan Winters