Civil Engineering Questions And Answers :: Construction Planning And Management: part1

Exam2win > Engineering > Civil Engineering > Construction Planning And Management > part1



Civil Engineering : Construction Planning And Management QUESTIONS AND ANSWERS :: part1 : 11 to 15

Following Civil Engineering Multiple choice objective type questions and answers will help you in BSNL JTO, GATE 2024 and IES 2024 examinations :

11.Whenever an activity has zero total float, then

free float of the activity must be zero but independent float need not be zero
independent float must be zero but free float need not be zero
free float and independent float both must be zero
free float and independent float both need not be zero

12.Select the incorrect statement.

Earliest start of an activity is the early event time of the node it leaves.
Latest finish of an activity is the late event time of the node it enters.
Latest start of an activity is its latest finish minus its duration.
none of the above

13.Select the incorrect statement.

Start float and finish float are always equal.
Total float can be either start float or finish float.
Start float and finish float need not be equal.
Start float and finish float are the differences between activity times and not event times.

14.In the network shown in Fig. , the critical path is

1-2-3-4-5-6
1-2-4-5-6
1-2-3-5-6
1-2-4-3-5-6

15.Total float for any activity is defined as the difference between

its latest finish time and earliest start time for its successor activity
its latest start time and earliest start time
its latest start time and earliest finish time
its earliest finish time and earliest start time for its successor activity

More Construction Planning And Management QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Identify your problems but give your power and energy to solutions- Tony Robbins