Civil Engineering Questions And Answers :: Construction Planning And Management: part2



Civil Engineering : Construction Planning And Management QUESTIONS AND ANSWERS :: part2 : 11 to 15

Following Civil Engineering Multiple choice objective type questions and answers will help you in BSNL JTO, GATE 2024 and IES 2024 examinations :

11.The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

total float
free float
interfering float
independent float

12.The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack Of these statements

(i), (ii) and (iv) are correct
(ii), (iii) and (iv) are correct
(i), (iii) and (iv) are correct
(i), (ii) and (iii) are correct

13.The normal time required for the comple-tion of project in the above problem is

9 days
13 days
14 days
19 days

14.For a given size of bucket, the ideal output of a dragline will be least in

Moist loam
Sand and gravel
Good common earth
Wet sticky clay

15.Assertion (A): Activity 5-7 is critical. Reason (R) : Earliest finish time and latest finish time for events 5-7 are same Select the correct answer.

A is correct but R is not correct
R is correct but A is not correct
both A and R are correct
both A and R are incorrect

More Construction Planning And Management QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Failure defeats losers, failure inspires winners.-Robert T. Kiyosaki