21.Updating may result in

change of critical path
decrease of project completion time
increase of project completion time
all of the above

22.The reduction in project time normally results in

decreasing the direct cost and increasing indirect cost
increasing the direct cost and decreasing the indirect cost
increasing the direct cost and indirect cost both
decreasing the direct cost and indirect cost both

23.Economic saving of time results by crashing

cheapest critical activity
cheapest non-critical activity
costliest critical activity
costliest non-critical activity

24.Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements

(ii), (iii) and (iv) are correct
(i), (ii) and (iv) are correct
(i), (iii) and (iv) are correct
(i) and (iv) are correct

25.For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

Moist loam
Good common earth
We|l blasted rock
Wet sticky clay

More Construction Planning And Management QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
If you are not willing to risk the usual you will have to settle for the ordinary- Jim Rohn