16.The first method invented for planning projects was

bar chart method
milestone chart
critical path method (CPM)
programmer evaluation and review technique (PERT)
none of the above.

17.The performance of a specific task in CPM is known as

dummy
event
activity
contract
none of the above.

18.Routing assists engineers in deciding in advance

the flow of material in the plant
the methods of proper utilization of manpower
the methods of proper utilization of machines
the layout of factory facilities
normal route of workers through the plant.

19.The time of completing a project in network analysis is given by following time of the critical activity meeting at the final iodide

early finish
early start
late start
late finish
none of the above.

20.If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

latest start time - earliest start time
latest finish time - earliest finish time (EFT)
TLEFT
all of the above
none of the above.

More Production Technology QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Trust because you are willing to accept the risk, not because it’s safe or certain