11.Bar charts are suitable for

minor works
major works
large projects
all of the above
none of the above.

12.The probability distribution of project completion in PERT follows following distribution

normal
binominal
beta
exponential
Gaussian.

13.Pick up the correct step used for scheduling a project by C.P.M.

a project is divided into various activities
required time for each activity is established
sequence of various activities is made according to their importance
network is drawn by connecting the activities and the events
all of the above.

14.The critical path of a network represents

the minimum time required for completion of project
the maximum time required for completion of project
maximum cost required for completion of project
minimum cost required for completion of project
none of the above.

15.Pick up the correct statement from the following

critical path method is an improvement upon bar chart method
critical path method provides a realistic approach to the daily problems
critical path method avoids delays which are very common in bar chart
critical path method was invented by Morgan R. Walker of Dupot and James E. Kelley of Remington U.S.A in 1957
all of the above.

More Production Technology QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Innovation distinguishes between a leader and a follower.-Steve Jobs