6.The probability distribution of activity times in PERT follows following distribution

normal
binomial
beta
exponential
Gaussian.

7.A milestone chart

shows the interdependences of various jobs
depicts the delay of jobs, if any
points outgoing ahead of schedule of jobs, if any
all of the above
none of the above.

8.The critical activity has

maximum float
inimum float
zero float,
average float
none of these.

9.If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

EF=ES+D
LS=LF-D
LF = LS + D
D = EF-ES
all of the above.

10.Emergency rush order can be pushed more effectively in

job production
automatic production
continuous production
intermittent production
none of the above.

More Production Technology QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Innovation distinguishes between a leader and a follower.-Steve Jobs