41. The probability distribution of project completion in PERT follows following distribution
A. normal
B. binominal
C. beta
D. exponential
E. Gaussian.
Explanation:
42. Pick up the correct step used for scheduling a project by C.P.M.
A. a project is divided into various activities
B. required time for each activity is established
C. sequence of various activities is made according to their importance
D. network is drawn by connecting the activities and the events
E. all of the above.
Explanation:
43. The critical path of a network represents
A. the minimum time required for completion of project
B. the maximum time required for completion of project
C. maximum cost required for completion of project
D. minimum cost required for completion of project
E. none of the above.
Explanation:
44. Pick up the correct statement from the following
A. critical path method is an improvement upon bar chart method
B. critical path method provides a realistic approach to the daily problems
C. critical path method avoids delays which are very common in bar chart
D. critical path method was invented by Morgan R. Walker of Dupot and James E. Kelley of Remington U.S.A in 1957
E. all of the above.
Explanation:
45. The first method invented for planning projects was
A. bar chart method
B. milestone chart
C. critical path method (CPM)
D. programmer evaluation and review technique (PERT)
E. none of the above.
Explanation: