156. The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as
A. Rowan Plan
B. Bedaux Plan
C. Taylor Differential Piece rate system
D. Halsey Premium plan
E. Day work plan.
Explanation:
157. For ship vessel industry the following layout is best suited
A. process layout
B. product layout
C. fixed position layout
D. plant layout
E. functional layout.
Explanation:
158. In Lincoln plan (one type of group incentive plan), the amount of the profit which an .employee receives in addition to the guaranteed basic pay/wages, is based on :
A. a standard rating system
B. a merit rating system
C. a job evaluation system
D. his individual performance
E. all of the above.
Explanation:
159. One of the basic essentials of an incentive plan is that
A. a differential piece rate system should exist
B. minimum wages should be guaranteed
C. provide incentive to group efficiency performance
D. all standards should be based on optimum standards of production
E. all standards should be based on time studies.
Explanation:
160. In the Halsey system of wage incentive plan, a worker is
A. paid as per efficiency
B. ensured of minimum wages
C. not paid any bonus till his efficiency
D. never a loser
E. induced to do more work.
Explanation: