81. Critical Path Net Work helps an engineer
A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. all of the above
E. none of the above.
Explanation:
82. Critical path moves along the activities having total float of
A. positive value
B. negative value
C. zero value
D. same value
E. none of the above.
Explanation:
83. Basic tool in work study is
A. graph paper
B. process chart
C. planning chart
D. stop watch
E. analytical mind.
Explanation:
84. Expediting function consists in keeping a watch on
A. operator's activity
B. flow of material and in case of trouble locate source of trouble
C. minimising the delays
D. making efficient despatching
E. none of the above.
Explanation:
85. The standard time for a job is
A. total work content
B. basic time + relaxation time
C. total work content + basic time
D. total work content + delay contingency allowance
E. total work content + relaxation time.
Explanation: