46. What does symbol 'D' imply in work study
A. inspection
B. transport
C. delay/temporary storage
D. permanent storage
E. none of the above.
Explanation:
47. The performance of a specific task in CPM is known as
A. dummy
B. event
C. activity
D. contract
E. none of the above.
Explanation:
48. Routing assists engineers in deciding in advance
A. the flow of material in the plant
B. the methods of proper utilization of manpower
C. the methods of proper utilization of machines
D. the layout of factory facilities
E. normal route of workers through the plant.
Explanation:
49. The time of completing a project in network analysis is given by following time of the critical activity meeting at the final iodide
A. early finish
B. early start
C. late start
D. late finish
E. none of the above.
Explanation:
50. If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
A. latest start time - earliest start time
B. latest finish time - earliest finish time (EFT)
C. TLEFT
D. all of the above
E. none of the above.
Explanation: