Mechanical Engineering Questions And Answers :: Production Technology: part4



Mechanical Engineering : Production Technology QUESTIONS AND ANSWERS :: part4 : 21 to 25

Following Mechanical Engineering Multiple choice objective type questions and answers will help you in BSNL JTO, GATE 2024 and IES 2024 examinations :

21.Tick the odd man out

Taylor
Drucker
McGregor
Galileo
Parkinson.

22.In Halsey 50-50 plan, output standards are established

by time study
from previous production records
from one's judgement
all of the above
none of the above.

23.The objective of time study is to determine the time required to complete a job by

fast worker
average worker
slow worker
new entrant
any one of the above.

24.PERT has following time estimate

one time estimate
two time estimate
three time estimate
four time estimate
nil time estimate.

25.In the Halsey 50-50 plan, the following are rewarded more

past good workers
past poor workers
past average workers
all of the above
none of the above.

More Production Technology QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Trust because you are willing to accept the risk, not because it’s safe or certain