6.PMTP (predetermined motion time systems) include

MTM (method time measurement)
WFS (work factor systems)
BNTS (basic motion time study)
all of the above
none of the abbvev

7.Which of the following equations is not in conformity with others

organisation performance x motivation = profits
knowledge x skill = ability
ability x motivation = performance
attitude x situation = motivation
performance x resources = organisation performance.

8.Queing theory is associated with

sales
inspection time
waiting time
production time
inventory.

9.Queing theory is used for

inventory problems
traffic congestion studies
job-shop scheduling
all of the above
none of the above.

10.The basic difference between PERT and CPM is that

PERT deals with events and CPM with activities
critical path is determined in PERT only
costs are considered on CPM only and not in PERT
guessed times are used in PERT and evaluated times in CPM
PERT is used in workshops and CPM in plants.

More Production Management And Industrial Engineering QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
If you are not willing to risk the usual you will have to settle for the ordinary- Jim Rohn