Mechanical Engineering Questions And Answers :: Production Management And Industrial Engineering: part5



Mechanical Engineering : Production Management And Industrial Engineering QUESTIONS AND ANSWERS :: part5 : 1 to 5

Following Mechanical Engineering Multiple choice objective type questions and answers will help you in BSNL JTO, GATE 2024 and IES 2024 examinations :

1.The two-bin system is concerned with

ordering procedure
forecasting sales
production planning
despatching and expediting
none of the above.

2.Slack represents the difference between the

latest allowable time and the normal expected time
latest allowable time and the earliest expected time
proposed allowable time and the ear-liest expected time
normal allowable time and the latest expected time
project initiation tune and actual starting time.

3.In Lincoln plan (one type of group incentive plan), the amount of the profit which an .employee receives in addition to the guaranteed basic pay/wages, is based on :

a standard rating system
a merit rating system
a job evaluation system
his individual performance
all of the above.

4.Which of the following plans motivates supervisors by paying a premium on time saved by workers

Halsey plan
Rowan plan
Haynes plan
Emerson's plan
Taylor's plan.

5.String diagram is used

for checking the relative values of various layouts
when a group of workers are working at a place
where processes require the operator to be moved from one place to another
all of the above
none of the above.

More Production Management And Industrial Engineering QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
The only place where success comes before work is in the dictionary.- Vidal Sassoon