31. PERT is the
A. time oriented technique
B. event oriented technique
C. activity oriented technique
D. target oriented technique
E. work oriented technique.
Explanation:
32. PMTP (predetermined motion time systems) include
A. MTM (method time measurement)
B. WFS (work factor systems)
C. BNTS (basic motion time study)
D. all of the above
E. none of the abbvev
Explanation:
33. Which of the following equations is not in conformity with others
A. organisation performance x motivation = profits
B. knowledge x skill = ability
C. ability x motivation = performance
D. attitude x situation = motivation
E. performance x resources = organisation performance.
Explanation:
34. Queing theory is associated with
A. sales
B. inspection time
C. waiting time
D. production time
E. inventory.
Explanation:
35. String diagram is used when
A. team of workers is working at a place
B. material handling is to be done
C. idle time is to be reduced
D. all of the above
E. none of the above.
Explanation: