Home > Mechanical Engineering > Production Management and Industrial Engineering

Production Management and Industrial Engineering - Interview Questions and Answers

Prepare for your technical interview with these Production Management and Industrial Engineering questions.

Ready to test your skills?

Take a timed mock test specifically for Production Management and Industrial Engineering.

Start Mock Test
1. Choose the wrong statement Time study is used to
A. determine overhead expenses
B. provide a basis for setting piece prices or incentive wages
C. determine standard costs
D. determine the capability of an operator to handle the number of machines
E. compare alternative methods.
Explanation:
2. Material handling in automobile industry is done by
A. overhead crane
B. trolley
C. belt conveyor
D. all of the above
E. none of the above.
Explanation:
3. In Lincoln plan (one type of group incentive plan), the amount of the profit which an .employee receives in addition to the guaranteed basic pay/wages, is based on :
A. a standard rating system
B. a merit rating system
C. a job evaluation system
D. his individual performance
E. all of the above.
Explanation:
4. Which of the following plans motivates supervisors by paying a premium on time saved by workers
A. Halsey plan
B. Rowan plan
C. Haynes plan
D. Emerson's plan
E. Taylor's plan.
Explanation:
5. String diagram is used
A. for checking the relative values of various layouts
B. when a group of workers are working at a place
C. where processes require the operator to be moved from one place to another
D. all of the above
E. none of the above.
Explanation: