Production Management and Industrial Engineering - Interview Questions and Answers

Prepare for your technical interview with these Production Management and Industrial Engineering questions.

Ready to test your skills?

Take a timed mock test specifically for Production Management and Industrial Engineering.

Start Mock Test
111. The objective of time study is to determine the time required to complete a job by
A. fast worker
B. average worker
C. slow worker
D. new entrant
E. any one of the above.
Explanation:
112. Standard time as compared to normal time is
A. greater
B. smaller
C. equal
D. there is no such correlation
E. none of the above.
Explanation:
113. Break-even analysis can be used for
A. short run analysis
B. long run analysis
C. average of above two run analysis
D. there is no such criterion
E. none of the above.
Explanation:
114. In the Halsey 50-50 plan, the following are rewarded more
A. past good workers
B. past poor workers
C. past average workers
D. all of the above
E. none of the above.
Explanation:
115. In crash programe for a project
A. both direct and indirect costs, increase
B. indirect costs increase and direct costs decrease
C. direct costs increase and indirect costs decrease
D. cost is no criterion
E. none of the above.
Explanation: