Electrical Engineering Questions And Answers :: Economics Of Power Generation: part1

Exam2win > Engineering > Electrical Engineering > Economics Of Power Generation > part1



Electrical Engineering : Economics Of Power Generation QUESTIONS AND ANSWERS :: part1 : 1 to 5

Following Electrical Engineering Multiple choice objective type questions and answers will help you in BSNL JTO, GATE 2024 and IES 2024 examinations :

1.In Hopknison demand rate or two parttariff the demand rate or fixed charges are

dependent upon the energy consumed
dependent upon the maximum demand of the consumer
both (a) and (b)
neither (a) nor (b)

2.Power plant having maximum demand more than the installed rated capacity will have utilisation factor

equal to unity
less than unity
more than unity
none of the above

3.Which plant can never have 100 percent load factor ?

Peak load plant
Base load plant
Nuclear power plant
Hydro electric plant

4.Maximum demand on a power plant is

the greatest of all "short time interval averaged" demand during a period
instantaneous maximum value of kVA supplied during a period
both (a) or (b)
none of the above

5.The area under a load curve gives

average demand
energy consumed
maximum demand
none of the above

More Economics Of Power Generation QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Identify your problems but give your power and energy to solutions- Tony Robbins