1.In Hopknison demand rate or two parttariff the demand rate or fixed charges are

dependent upon the energy consumed
dependent upon the maximum demand of the consumer
both (a) and (b)
neither (a) nor (b)

2.Power plant having maximum demand more than the installed rated capacity will have utilisation factor

equal to unity
less than unity
more than unity
none of the above

3.Which plant can never have 100 percent load factor ?

Peak load plant
Base load plant
Nuclear power plant
Hydro electric plant

4.Maximum demand on a power plant is

the greatest of all "short time interval averaged" demand during a period
instantaneous maximum value of kVA supplied during a period
both (a) or (b)
none of the above

5.The area under a load curve gives

average demand
energy consumed
maximum demand
none of the above

More Economics Of Power Generation QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
A real entrepreneur is somebody who has no safety net underneath them. Henry Kravis