16.For the upstream face of an earthen dam, the most adverse condition for stability of slope is

sudden drawdown
steady seepage
during construction
sloughing of slope

17.Seepage through embankments in an earthen dam is controlled by

drainage filters
relief wells
drain trenches
provision of downstream berms

18.Presence of tail water in a gravity dam i) increases the principal stress ii) decreases the principal stress iii) increases the shear stress iv) decreases the shear stress The correct answer is

(i) and (iii)
(i)and(iv)
(ii) and (iii)
(ii) and (iv)

19.The flow of water after spilling over the weir crest in chute spillway and side channel spillway respectively are

at right angle and parallel to weir crest
parallel and at right angle to weir crest
parallel to weir crest in both
at right angle to weir crest in both

20.In a chute spillway, the flow is usually

uniform
subcritical
critical
super critical

More Irrigation Water Resources Engineering QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Identify your problems but give your power and energy to solutions- Tony Robbins