6.The uplift pressure on a dam can be controlled by i) constructing cutoff under upstream face ii) constructing drainage channels bet-ween the dam and its foundation iii) by pressure grouting in foundation The corret answer is

only (i)
both (i) and (ii)
both (i) and (iii)
(i), (ii) and (iii)

7.For a flood control reservoir, the effective storage is equal to

useful storage - valley storage
useful storage + surcharge storage
useful storage + surcharge storage + valley storage
useful storage + surcharge storage -valley storage

8.The useful storage is the volume of water stored in the reservoir between

minimum pool level and maximum pool level
minimum pool level and normal pool level
normal pool level and maximum pool level
river bed and minimum pool level

9.The relation between probability (P) and recurrence interval (T) is given by

PT = 1
PT2 = 1
P/T = 1
P/T2 = 1

10.Trap efficiency of a reservoir is a function of

capacity/inflow ratio
capacity/outflow ratio
outflow/inflow ratio
none of the above

More Irrigation Water Resources Engineering QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
The only place where success comes before work is in the dictionary.- Vidal Sassoon