Civil Engineering Questions And Answers :: Surveying: part5



Civil Engineering : Surveying QUESTIONS AND ANSWERS :: part5 : 1 to 5

Following Civil Engineering Multiple choice objective type questions and answers will help you in BSNL JTO, GATE 2024 and IES 2024 examinations :

1.If in a closed traverse, the sum of the north latitudes is more than the sum of the south latitudes and also the sum of west departures is more than the sum of the east departures, the bearing of the closing line is in the

NE quadrant
SE quadrant
NW quadrant
SW quadrant

2.The two point problem and three point problem are methods of

resection
orientation
traversing
resection and orientation

5.If the reduced bearing of a line AB is N60�W and length is 100 m, then the latitude and departure respectively of the line AB will be

+50 m, +86.6 m
+86.6 m, -50 m
+50m, -86.6 m
+70.7 m,-50 m

More Surveying QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
Too many of us are not living our dreams because we are living our fears.- Les Brown