Time And Work QUESTIONS AND ANSWERS :: Arithmetic : part2 : 6 to 10
Following Time And Work multiple choice objective type questions and answers will help you in many types of 2024 job and other entrance examinations :
6.A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is: |
6 days |
8 days |
10 days |
13 days |
7.12 men or 18 women can reap a field in 14 days. The number of days that 8 men and 16 women will take to reap it, is: |
5 |
7 |
8 |
9 |
8.A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately. A beginning, in how many days the work will be completed? |
10 days |
10 days |
10 days |
10 days |
More Time And Work QUESTIONS AND ANSWERS available in next pages
-
Health is the greatest gift, contentment is the greatest wealth -Buddha
- TNTET 2021 - Practice
- SSC CGL 2021 - Practice
- TNPSC Group 2A 2021 - Practice
- IIT JEE
- IIT JEE Q&A
- TNPSC Answer Keys
- TNPSC Group 2 Syllabus
- TNPSC Q&A
- Online Tests - TNPSC
- Online Tests - GK
- IBPS 2020-2021
- Online Tests - Bank
- Online Tests - RRB NTPC
- Online Tests - UGC NET
- Online Tests - TANCET
- Online Aptitude Test
- Engineering
- Programming
- Basic Science
- Quiz
- Plus Two Question Papers
- SSLC Question Bank
- Aptitude Tests
- Logical Reasoning
- General Knowledge-Hindi
- Indian History MCQ
- Indian Geography MCQ
- Indian Civics MCQ
- Indian Economics MCQ
- CTET Biology MCQ
- CTET Chemistry MCQ
- CTET Physics Solved MCQ
- Arithmetic Tests
- Press Release
- FAQ
- Coaching Centres
- TNPSC Group 1 Syllabus
- TNPSC Group IV Syllabus
- TRB 2017 in English PDF
- TRB 2017 in Tamil PDF
- TET
- TNTET