86. The average ash content in Indian co als is about
A. 5%
B. 10%
C. 15%
D. 20%
Explanation:
87. Example of overfeed type stoker is
A. chain grate
B. spreader
C. travelling grate
D. all of the above
Explanation:
88. The proper indication of incomplete combustion is
A. high CO content in flue gases at exit
B. high CO2 content in flue gases at exit
C. high temperature of flue gases
D. the smoking exhaust from chimney