Home > Electrical Engineering > Power Plant Engineering

Power Plant Engineering - Interview Questions and Answers

Prepare for your technical interview with these Power Plant Engineering questions.

Ready to test your skills?

Take a timed mock test specifically for Power Plant Engineering.

Start Mock Test
81. In coal preparation plant, magnetic separators are used to remove
A. dust
B. clinkers
C. iron particles
D. sand
Explanation:
82. Load centre in a power station is
A. centre of coal fields
B. centre of maximum load of equip-ments
C. centre of gravity of electrical system
D. centre of gravity of electrical system
Explanation:
83. The value of the reheat factor is of the order of
A. 0.8 to 1.0
B. 1.0 to 1.05
C. 1.1 to 1.5
D. above 1.5
Explanation:
84. The efficiency of a modern boiler using coal and heat recovery equipment is about
A. 25 to 30%
B. 40 to 50%
C. 65 to 70%
D. 85 to 90%
Explanation:
85. Load carrying capacity of belt conveyor is about
A. 20 to 40 tonnes/hr
B. 50 to 100 tonnes/hr
C. 100 to 150 tonnes/hr
D. 150 to 200 tonnes/hr
Explanation: