Civil Engineering Questions And Answers :: Construction Planning And Management: part1

Exam2win > Engineering > Civil Engineering > Construction Planning And Management > part1



Civil Engineering : Construction Planning And Management QUESTIONS AND ANSWERS :: part1 : 21 to 25

Following Civil Engineering Multiple choice objective type questions and answers will help you in BSNL JTO, GATE 2024 and IES 2024 examinations :

21.If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

expected time of activity A is greater than the expected time of activity B
expected time of activity B is greater than the expected time of activity A
expected time of both activities A and B are same
none of the above

22.According to Fulkerson's rule, what are the correct event numbers corresponding to events A, B, C, D,E, F and G of the network shown in Fig. ?

1, 2,3, 4, 5, 6 and 7 respectively
1, 3,2,4, 5,6 and 7 respectively
1,2, 3, 5, 6,4 and 7 respectively
1, 3,2, 5, 6,4 and 7 respectively

23.In the network shown in Fig. the earliest start time of activity 5-6 is (the number on the arrow shows duration of the activity)

7
8
9
5

24.With reference to the network shown in Fig. , which statement is incorrect ?

Events 3 and 4 occur after event 2.
Event 7 can occur after event 4.
Event 7 precedes event 6.
Event 5 follows event 3.

More Construction Planning And Management QUESTIONS AND ANSWERS available in next pages

    Health is the greatest gift, contentment is the greatest wealth -Buddha
The only place where success comes before work is in the dictionary.- Vidal Sassoon